Darlington Refurbishment reports

Learn more about Ontario Power Generation’s Darlington Refurbishment Project, one of Canada’s largest clean-energy initiatives, by exploring progress reports on how we’re delivering this complex project.

News update

Darlington Refurbishment performance update - Q3 2021

As we being the reassembly phase on Unit 3, the project team prepares for Unit 1, which is set to begin refurbishment in February 2022.

Read more
News update

Darlington Refurbishment performance update - Q2 2021

We continue to make safe, steady progress on Unit 3 due to the tremendous efforts of thousands of project partners, suppliers and workers.

Read more
News update

Darlington Refurbishment performance update - Q1 2021

Several months into 2021, the project has already completed a tremendous amount of work safely, ahead of schedule and on budget.

Read more
Our projects

Darlington Refurbishment performance update - Q4 2020

Despite the challenges associated with the COVID-19 pandemic, the Darlington Refurbishment project remains ahead of schedule and on budget.

Read more
Our projects

Darlington Refurbishment performance update - Q3 2020

Learn about the 2020 third quarter performance of the Darlington Refurbishment, one of Canada’s largest clean energy projects.

Read more
Our projects

Darlington Refurbishment performance update - Q2 2020

Learn about the 2020 second quarter performance of the Darlington Refurbishment, one of Canada’s largest clean energy projects.

Read more
Results 1-6 of 11