December 2017 Project Performance Update

 December 2017 Project Performance Update

RT @leaf: Have you heard about our new partnership with @TWC_Wildlife ? With support from @opg we're spreading the word about #BackyardBiod…

Tue Jun 19 19:58:26

The summer edition of #PowerNews is here. See how we took a dive with a mini yellow submarine, harvested Cobalt-60… https://t.co/ImXwf7YU5S

Tue Jun 19 19:30:14

RT @PlugN_Drive: Say hi to the #OPGBOLT and staff at @OPG Renfrew! Everyone was all smiles today while learning about #ElectricVehicles and…

Tue Jun 19 19:24:44

 

2/13/2018      

 

Key Performance Indicators (KPIs) are an important part of OPG’s strategy to ensure our commitments are met, evaluate performance against plan and guide our decision-making regarding any necessary course adjustments.

Worker safety performance improved overall in December 2017. The Safety Stand Down in November and associated measures put in place contributed to the improvement in safety performance.

Since Unit 2 Breaker Open, Oct. 14, 2016, the team has safely worked 6.5 million hours on all nuclear refurbishment projects without a lost time accident.

The End Fitting Removal series continued in December, and the Pressure Tube Removal series commenced on Jan. 21.

Unit 2 refurbishment costs were $33 Million below plan. 

For an overview of our December 2017 KPIs, please read this infographic.