December 2017 Project Performance Update

 December 2017 Project Performance Update

@bythelake6 Hi Paul, You’re right, sometimes we nerd out. Neutron flux means “intensity”. CANDU reactors emit a lar… https://t.co/6w87NmFVj9

Tue Dec 11 21:48:48

This hungry little guy is trying to grab a bite. Piping Plovers are making a comeback in Ontario, thanks to… https://t.co/49xo2z5dhK

Tue Dec 11 20:55:43

Amazing shot! https://t.co/Gx8PM9QEco

Tue Dec 11 18:25:00

 

2/13/2018      

 

Key Performance Indicators (KPIs) are an important part of OPG’s strategy to ensure our commitments are met, evaluate performance against plan and guide our decision-making regarding any necessary course adjustments.

Worker safety performance improved overall in December 2017. The Safety Stand Down in November and associated measures put in place contributed to the improvement in safety performance.

Since Unit 2 Breaker Open, Oct. 14, 2016, the team has safely worked 6.5 million hours on all nuclear refurbishment projects without a lost time accident.

The End Fitting Removal series continued in December, and the Pressure Tube Removal series commenced on Jan. 21.

Unit 2 refurbishment costs were $33 Million below plan. 

For an overview of our December 2017 KPIs, please read this infographic.

In addition to monthly KPI updates, OPG releases quarterly reports and electronic newsletters about the progress of the Darlington Refurbishment project. For more information, please visit www.opg.com/darlingtonrefurb