December 2017 Project Performance Update

 December 2017 Project Performance Update

Visiting schools across @CityThunderBay, our Northwest Operations staff teach kids to #stayclearstaysafe of hydro s…

Tue Mar 20 19:06:14

The Spring issue of PowerNews has updates on #DarlingtonRefurb, the Beck Power Canal, and the Nanticoke stack demo,…

Tue Mar 20 17:45:55

Our sites are home to many different species, like the Chorus Frog, Spring Peeper, Northern Leopard Frog, Green Fro…

Tue Mar 20 17:04:31




Key Performance Indicators (KPIs) are an important part of OPG’s strategy to ensure our commitments are met, evaluate performance against plan and guide our decision-making regarding any necessary course adjustments.

Worker safety performance improved overall in December 2017. The Safety Stand Down in November and associated measures put in place contributed to the improvement in safety performance.

Since Unit 2 Breaker Open, Oct. 14, 2016, the team has safely worked 6.5 million hours on all nuclear refurbishment projects without a lost time accident.

The End Fitting Removal series continued in December, and the Pressure Tube Removal series commenced on Jan. 21.

Unit 2 refurbishment costs were $33 Million below plan. 

For an overview of our December 2017 KPIs, please read this infographic.

In addition to monthly KPI updates, OPG releases quarterly reports and electronic newsletters about the progress of the Darlington Refurbishment project. For more information, please visit